How Long Does It Take to Make a Custom Cartoon Sculpture?

2026-09-10

A large cartoon dog sculpture under construction in a fabrication workshop, with a steel frame and a fibreglass mould behind it

It is the first question almost every client asks, usually the same afternoon they send their first photos. The honest answer for a large piece is eight to sixteen weeks, and the two things that decide where in that range you land are size and material.

The short answer

  • A 1.5–2.0 m fibreglass sculpture: 6–9 weeks.
  • 2.0–3.0 m in fibreglass: 9–12 weeks.
  • Anything above 3 m: 12–18 weeks, because the piece is built in sections.
  • Stainless steel: add roughly 4–8 weeks at every size, because the form is fabricated and welded rather than moulded.

Week by week

Weeks 1–2 — photos and quote

You send photographs, we assess what can and cannot be read from them, and you get a fixed written quote. This stage is fast, and it is free. It is also where a project is most likely to be quietly wrong: if the photographs cannot support the detail you want, better to hear it now.

Weeks 2–4 — the 3D model

We build the piece in three dimensions from your photographs and send you renders from several angles. You approve, or you ask for changes. Nothing goes into production without your sign-off, and this is the stage where revisions are cheap. Two rounds are included.

Weeks 4–9 — the full-size build

The approved model is scaled up and the form is sculpted at full size over an internal steel frame. For fibreglass that means a pattern and then a mould; for stainless it means forming and welding sheet and tube. Above 2 m the frame is engineered, which is why this stage is where the schedule is won or lost.

Weeks 9–12 — mould, layup and finishing

Fibreglass is laminated into the mould, released, and finished in multi-layer automotive paint with hand-painted detail and a UV clear coat. Stainless is ground, welded, ground again, and then brushed or polished. Finishing is the slowest hand-work in the whole project, and it is the stage people underestimate.

Weeks 12–16 — crating and delivery

Custom crate, export documentation, freight, and — above 2.5 m — on-site assembly. Sea freight for a large piece runs four to eight weeks depending on destination, and that time sits outside the build schedule.

What actually slows a project down

  • Undecided design. Every week spent choosing a pose or a colour is a week added. The 3D stage is cheap to revise; the full-size stage is not.
  • Size above 2 m. Structural drawings, sectioned builds and site welding all add time that cannot be compressed.
  • Poor photographs. If we have to ask for better references mid-project, the clay or 3D stage stops while we wait.
  • Site access. A piece that needs a crane and a road closure needs coordinating, and that coordination sets the delivery date rather than the workshop.

What does not affect the timeline

Colour complexity, the number of painted markings and the pose you choose barely move the schedule — they change the cost, not the calendar. A brindle staffie takes about the same time to build as a plain one.

If you have a fixed date in mind, say so at the start. It is far easier to plan around a deadline than to recover one.